Rack Power Calculator

Estimate a server rack's IT load, facility load with PUE, cooling demand in BTU per hour and monthly electricity cost. PUE scales facility energy, not the equipment's own watts.

Result

IT load1.20 kW
Facility load1.68 kW
IT heat4,095 BTU/hr
Monthly energy1,226 kWh
Monthly cost$183.86

Note: Monthly figures use 30.4 days.

Learn more

How it works

Enter the power your IT gear draws, your facility's PUE and your electricity price.

  • Facility load = IT load x PUE. PUE (power usage effectiveness) covers cooling, UPS losses and lighting: a PUE of 1.4 means every 1 kW of IT load needs 1.4 kW at the meter.
  • Heat: nearly all the power a server uses ends up as heat. 1 watt = 3.41214 BTU/hr, the unit cooling equipment is rated in.
  • Monthly energy = facility kW x 24 hours x 30.4 days.
Worked example

The default is a rack drawing 1,200 W, with a PUE of 1.4 and power at $0.15 per kWh:

  • Facility load: 1.2 kW x 1.4 = 1.68 kW
  • Heat: 1,200 x 3.41214 = 4,095 BTU/hr, about a third of a ton of cooling (1 ton = 12,000 BTU/hr)
  • Energy: 1.68 x 24 x 30.4 = 1,225.7 kWh per month (shown as 1,226)
  • Cost: 1,225.7 x $0.15 = $183.86 per month
What PUE should I use?

Use your facility's measured figure if you have it. Large modern data centers report 1.1 to 1.4. A server closet with a room air conditioner is often 1.8 or higher.

How big a circuit does the rack need?

In the US, the electrical code limits continuous loads to 80% of the breaker rating. A 20 A, 208 V circuit gives 20 x 208 x 0.8 = 3,328 W of usable power. Check local code and your PDU rating.

Should I use nameplate watts?

No. Power supply ratings are far above typical draw. Use readings from a metered PDU, the UPS display or the servers' management pages for a realistic figure.